Mengyin Cogeneration Project Design

Construction unit: Mengyin Xiangtai Energy Co.

Project Location: Mengyin County, Linyi City, Shandong Province, China

Planned investment: about 650 million yuan

Design content: heat source plant, heating station, steam pipe network design of a full set of construction drawings

Project Director: Shi Derui

Design period: 5 months for heat source plant, 4 months for heat supply first station and heat supply pipe network.

Completion date: March 2021


Contact Now E-Mail WhatsApp
Product Details

Construction content: 2x150t/h+2x200t/h high-temperature and high-pressure circulating fluidized bed boiler+1xCB20MW pumping back-pressure turbine-generator unit+1xB50MW pumping back-pressure unit, supporting 8 million m2 heating head station, and 25km of medium pressure and low pressure steam pipeline, steam header DN1100, hot water supply and return pipeline DN900, steam piping Pipe diameter DN150~DN500.